Rural Municipality of Wallace Water Supply

Virden, Manitoba

completeDrinking WaterCC
Federal contribution
$2.0M
$1,990,838
Federal share33%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Sep 1, 2009(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction end5 months earlyforecast Dec 31, 2011