Ninette Lagoon

Dunrea, Manitoba

completeWastewaterCC Top Up
Federal contribution
$578,055
Federal share22%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jun 3, 2010(actual)
Construction end
Oct 24, 2011(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Sep 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25005 in the federal list. How to read these figures.