Westside Water Co-op Ltd. - Rural Water Pipeline
Federal contribution
$2.9M
$2,851,200
Federal share33%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Cypress
- Construction start
- Apr 30, 2010(actual)
- Construction end
- Oct 30, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25031 in the federal list. How to read these figures.