Austin Community Building

MacGregor, Manitoba

completeRecreationCC Top Up
Federal contribution
$108,217
Federal share33%

of $324.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Sep 1, 2009(actual)
Construction end
Jun 11, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 15, 2009
  • Construction end3 months earlyforecast Aug 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25150 in the federal list. How to read these figures.