Town of Leaf Rapids - Recycling Building
Federal contribution
$28,022
Federal share29%
of $97.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Leaf Rapids
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction end6 months lateforecast Dec 31, 2009