Water Use Monitoring

Strome, Alberta

completeDrinking WaterCC
Federal contribution
$31,050
Federal share33%

of $93.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.6 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Strome
Construction start
Apr 12, 2010(actual)
Construction end
Jun 2, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Sep 1, 2009
  • Construction end5 months lateforecast Dec 31, 2009