RM of Armstrong Flood Mitigation Infrastructure
Federal contribution
$114,487
Federal share33%
of $343.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Armstrong
- Construction start
- Oct 27, 2009(actual)
- Construction end
- Jan 19, 2016(actual)
Against the original forecast
- Construction end2.2 years lateforecast Oct 31, 2013
Also in Inwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25190 in the federal list. How to read these figures.