Clairmont Main Lift Station Upgrading and Force Main - Grande Prairie

Clairmont, Alberta

completeWastewaterCC Top Up
Federal contribution
$898,443
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 19, 2009(actual)
Construction end
Sep 29, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2009
  • Construction end6 months lateforecast Mar 31, 2011

Also in Clairmont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25254 in the federal list. How to read these figures.