Local Road Improvement/Low Level Crossing
Federal contribution
$55,821
Federal share25%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Rural Municipality of Fisher
- Construction start
- Oct 6, 2010(actual)
- Construction end
- Feb 12, 2013(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 31, 2012
Also in Fisher Branch
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25259 in the federal list. How to read these figures.