Local Road Improvement/Low Level Crossing

Fisher Branch, Manitoba

completeHighways and RoadsCC Top Up
Federal contribution
$55,821
Federal share25%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 6, 2010(actual)
Construction end
Feb 12, 2013(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 31, 2012

Also in Fisher Branch

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25259 in the federal list. How to read these figures.