Village of Riverton - Lagoon Expansion
Federal contribution
$262,151
Federal share18%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Riverton
- Construction start
- Aug 7, 2011(actual)
- Construction end
- Jun 30, 2012(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 1, 2011
Also in Bifrost-Riverton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25364 in the federal list. How to read these figures.