Recreation Centre Renewal

Wabowden, Manitoba

completeRecreationCC
Federal contribution
$449,560
Federal share29%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
201020112012201320142015
Built
Program
Building Canada Fund - Communities Component
Construction start
Sep 30, 2013(actual)
Construction end
Mar 24, 2015(actual)

Against the original forecast

  • Construction end4 months lateforecast Nov 30, 2014