Back to projects

Wastewater Stabilization Pond

Cremona, Alberta

completeWastewaterCC
Federal contribution
$131,760
Federal share33%

of $395.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20152016
Built

Approved 23 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Cremona
Construction start
Oct 1, 2014(actual)
Construction end
Oct 26, 2015(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2014

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25605 in the federal list. How to read these figures.