Magrath Treatment Plant and Supply System Upgrade

Magrath, Alberta

completeDrinking WaterCC
Federal contribution
$1.8M
$1,798,055
Federal share33%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2010
2010201120122013
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Magrath
Construction start
Jan 10, 2011(actual)
Construction end
May 28, 2013(actual)

Against the original forecast

  • Construction start15 months lateforecast Oct 23, 2009
  • Construction end2.5 years lateforecast Dec 1, 2010

Also in Magrath

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25730 in the federal list. How to read these figures.