Water Storage and Distribution improvements
Federal contribution
$1.3M
$1,274,224
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Rimbey
- Construction start
- Mar 24, 2010(actual)
- Construction end
- Dec 28, 2011(actual)
Against the original forecast
- Construction end12 months lateforecast Jan 1, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25802 in the federal list. How to read these figures.