Infrastructure Study
Federal contribution
$7,218
Federal share33%
of $21.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.6 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Arrowwood
- Construction start
- Apr 9, 2010(actual)
- Construction end
- Aug 26, 2010(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2009
- Construction end12 months lateforecast Aug 12, 2009
Also in Arrowwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25827 in the federal list. How to read these figures.