Water and Wastewater Eastside Servicing

Sundre, Alberta

completeDrinking WaterCC
Federal contribution
$2.6M
$2,586,853
Federal share33%

of $7.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Sundre
Construction start
Jul 17, 2010(actual)
Construction end
Dec 31, 2013(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 1, 2009
  • Construction end2.3 years lateforecast Sep 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25831 in the federal list. How to read these figures.