Worsley Water Treatment Plant
Federal contribution
$1.3M
$1,266,666
Federal share32%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipal District of Clear Hills No. 21
- Construction start
- Jul 7, 2010(actual)
- Construction end
- Feb 7, 2013(actual)
Against the original forecast
- Construction start11 months lateforecast Aug 5, 2009
- Construction end3 months lateforecast Oct 31, 2012
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25881 in the federal list. How to read these figures.