Back to projects

Buffalo Lake Metis Settlement Museum & Cultural Interpretative Centre

Caslan, Alberta

completeCultureCC Top Up
Federal contribution
$1.1M
$1,093,713
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Sep 29, 2009(actual)
Construction end
Oct 31, 2011(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25892 in the federal list. How to read these figures.