Sidney - Lochside Waterfront Walkway Revitilization

Sidney, British Columbia

completeActive TransportationCC Top Up
Federal contribution
$374,171
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Sidney
Construction start
Aug 9, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Feb 15, 2010