Back to projects

Elnora Water and Wastewater

Elnora, Alberta

completeWastewaterCC
Federal contribution
$131,118
Federal share33%

of $393.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2010
2011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Elnora
Construction start
Jul 15, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2012

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26011 in the federal list. How to read these figures.