CLV Water System Upgrading

Morrin, Alberta

completeDrinking WaterCC
Federal contribution
$418,333
Federal share21%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016
Built

Approved 3 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Starland
Construction start
May 13, 2013(actual)
Construction end
Aug 31, 2014(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2013
  • Construction end2 months earlyforecast Oct 31, 2014

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26114 in the federal list. How to read these figures.