Federal contribution
$493,600
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of White Rock
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Oct 31, 2011(actual)