Relocation of the Town of Strathmore Wastewater Outfall
Federal contribution
$709,825
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Strathmore
- Construction start
- Sep 8, 2010(actual)
- Construction end
- Oct 4, 2013(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 1, 2010
- Construction end18 months lateforecast Mar 31, 2012
Also in Strathmore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26207 in the federal list. How to read these figures.