Willow Street & Greenwood Drive Reconstruction
Summerside, Prince Edward Island
Federal contribution
$570,000
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Summerside
- Construction start
- Jun 10, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 30, 2009
- Construction end14 months lateforecast Aug 30, 2010
Also in Summerside
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26267 in the federal list. How to read these figures.