Trunk Sewer - Phase I

Westville, Nova Scotia

completeWastewaterCC Top Up
Federal contribution
$303,622
Federal share33%

of $910.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Westville
Construction start
Jun 15, 2010(actual)
Construction end
Nov 18, 2010(actual)

Against the original forecast

  • Construction start11 months lateforecast Jul 15, 2009
  • Construction end14 months lateforecast Sep 30, 2009

Also in Westville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26272 in the federal list. How to read these figures.