Trunk Sewer - Phase I
Federal contribution
$303,622
Federal share33%
of $910.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Westville
- Construction start
- Jun 15, 2010(actual)
- Construction end
- Nov 18, 2010(actual)
Against the original forecast
- Construction start11 months lateforecast Jul 15, 2009
- Construction end14 months lateforecast Sep 30, 2009
Also in Westville