Hamlet of Emerald Park Rural Water Distribution
Federal contribution
$588,000
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Edenwold
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2009
- Construction end18 months earlyforecast Mar 31, 2013
Also in Balgonie