Complete West End Walkway and Shoreline Protection
Summerside, Prince Edward Island
Federal contribution
$1.2M
$1,200,000
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Summerside
- Construction start
- Oct 26, 2009(actual)
- Construction end
- Oct 30, 2012(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 31, 2009
- Construction end12 months lateforecast Oct 31, 2011
Also in Summerside