Back to projects

Complete Rebuild of Water Street Downtown Core

Summerside, Prince Edward Island

completeHighways and RoadsCC
Federal contribution
$354,777
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Summerside
Construction start
Jul 5, 2010(actual)
Construction end
Aug 31, 2011(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 30, 2009
  • Construction end4 weeks lateforecast Jul 31, 2011

Also in Summerside

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26373 in the federal list. How to read these figures.