Complete Rebuild of Water Street Downtown Core
Summerside, Prince Edward Island
Federal contribution
$354,777
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Summerside
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 30, 2009
- Construction end4 weeks lateforecast Jul 31, 2011
Also in Summerside