Clay capping of road to Organized Hamlet of Hitchcock Bay
Federal contribution
$99,492
Federal share33%
of $298.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Coteau
- Construction start
- Oct 27, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 30, 2009
- Construction end2.2 years earlyforecast Mar 31, 2013
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26407 in the federal list. How to read these figures.