Harvey Station Cedar Wood Waste Removal, Demonstration of Innovative Brownfield Redevelopment

Harvey, New Brunswick

completeBrownfield Remediation And RedevelopmentCC Top Up
Federal contribution
$64,322
Federal share33%

of $193.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Harvey
Construction start
Dec 2, 2009(actual)
Construction end
Nov 21, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 1, 2009
  • Construction end3 months lateforecast Aug 31, 2010

Also in Harvey

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26454 in the federal list. How to read these figures.