Back to projects

Construct new treatment & storage facility and pipeline

Maryfield, Saskatchewan

completeDrinking WaterCC
Federal contribution
$604,126
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Maryfield
Construction start
Oct 15, 2010(actual)
Construction end
Nov 7, 2012(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 22, 2009
  • Construction end4 months lateforecast Jun 30, 2012