Construct new treatment & storage facility and pipeline
Federal contribution
$604,126
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Maryfield
- Construction start
- Oct 15, 2010(actual)
- Construction end
- Nov 7, 2012(actual)
Against the original forecast
- Construction start16 months lateforecast Jun 22, 2009
- Construction end4 months lateforecast Jun 30, 2012