Water System Improvements for Distribution
Summerside, Prince Edward Island
Federal contribution
$60,258
Federal share25%
of $241.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Seawood Water Utility Corporation
- Construction start
- Oct 21, 2009(actual)
- Construction end
- Dec 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 30, 2009
- Construction end3 months lateforecast Oct 1, 2011