Dundurn Rural Water Utility Potable Water
Federal contribution
$7.1M
$7,072,712
Federal share33%
of $21.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Dundurn Rural Water Utility Board
- Construction start
- Apr 6, 2010(actual)
- Construction end
- Oct 28, 2016(actual)
Against the original forecast
- Construction start9 months lateforecast Jun 22, 2009