Water and Sewer

Happy Valley-Goose Bay, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$317,842
Federal share22%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Oct 1, 2015(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction end11 months lateforecast Mar 31, 2016