Water and Sewer Improvements
Norman's Cove-Long Cove, Newfoundland and Labrador
Federal contribution
$366,372
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Norman's Cove-Long Cove
- Construction start
- Jan 1, 2010(actual)
- Construction end
- Jul 24, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Oct 1, 2009
- Construction end6 months lateforecast Jan 31, 2010
Also in Norman's Cove-Long Cove