Schedule

Announced and approvedMay 14, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Northern Arm
Construction start
Aug 16, 2010(actual)
Construction end
Aug 26, 2013(actual)

Against the original forecast

  • Construction start10 months lateforecast Oct 30, 2009
  • Construction end3.6 years lateforecast Jan 31, 2010