Water and Road Upgrades

Channel-Port aux Basques, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$413,904
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 19, 2010(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2010
  • Construction end11 months lateforecast Mar 31, 2016