Water and Sewer Services, Phase 1 & 2, Areas 1 & 2
Badger's Quay, Newfoundland and Labrador
Federal contribution
$1.6M
$1,576,603
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
20102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of New-Wes-Valley
- Construction start
- Mar 8, 2010(actual)
- Construction end
- Sep 14, 2014(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 30, 2009
- Construction end22 months lateforecast Nov 1, 2012
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26739 in the federal list. How to read these figures.