Back to projects

West Pubnico Wastewater Treatment Facility Upgrade

Tusket, Nova Scotia

completeWastewaterCC Top Up
Federal contribution
$1.5M
$1,500,000
Federal share33%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
May 19, 2010(actual)
Construction end
May 27, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2010
  • Construction end5 weeks earlyforecast Jun 30, 2011

Also in Tusket