Hamlet of Bellevue - Lift Station
Federal contribution
$40,583
Federal share33%
of $121.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Rural Municipality of ST. LOUIS
- Construction start
- Jul 1, 2010(actual)
- Construction end
- Mar 2, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2010
- Construction end4 weeks earlyforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26816 in the federal list. How to read these figures.