Back to projects

Hamlet of Bellevue - Lift Station

Hoey, Saskatchewan

completeWastewaterCC Top Up
Federal contribution
$40,583
Federal share33%

of $121.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 1, 2010(actual)
Construction end
Mar 2, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2010
  • Construction end4 weeks earlyforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26816 in the federal list. How to read these figures.