Connection of Production Wells to Distribution System
Federal contribution
$1.6M
$1,621,077
Federal share33%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Baddeck
- Construction start
- May 2, 2012(actual)
- Construction end
- Dec 28, 2013(actual)
Against the original forecast
- Construction end7 months lateforecast May 30, 2013
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26894 in the federal list. How to read these figures.