Parkland Regional Waste Management Landfill

Sturgis, Saskatchewan

completeSolid Waste ManagementCC
Federal contribution
$62,000
Federal share33%

of $186.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 18, 2010(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start14 months lateforecast Jun 22, 2009
  • Construction end2.3 years earlyforecast Mar 31, 2013