Federal contribution
$26,666
Federal share33%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Star City
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Mar 15, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Aug 1, 2009
- Construction end2 years earlyforecast Mar 31, 2013