Eaton Park Seawall Restoration
Federal contribution
$61,203
Federal share33%
of $183.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Pugwash
- Construction start
- Feb 10, 2010(actual)
- Construction end
- Jul 23, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Sep 1, 2009
- Construction end7 months lateforecast Dec 31, 2009
Also in Pugwash
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26942 in the federal list. How to read these figures.