Water Treatment Upgrade - Village of Pelly
Federal contribution
$28,450
Federal share33%
of $85.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Pelly
- Construction start
- Aug 2, 2011(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start15 months lateforecast May 1, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26986 in the federal list. How to read these figures.