Sask. Landing Regional Water Pipeline Rural System

Elrose, Saskatchewan

completeDrinking WaterCC
Federal contribution
$7.7M
$7,745,153
Federal share33%

of $23.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 20, 2012(actual)
Construction end
Nov 5, 2015(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 30, 2012
  • Construction end8 weeks earlyforecast Dec 31, 2015

Also in Elrose

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27141 in the federal list. How to read these figures.