Alpine Crescent Underground Utilities Construction

Allan, Saskatchewan

completeDrinking WaterCC Top Up
Federal contribution
$99,787
Federal share33%

of $299.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Allan
Construction start
Sep 1, 2009(actual)
Construction end
Mar 23, 2010(actual)

Against the original forecast

  • Construction start8 months earlyforecast May 1, 2010
  • Construction end12 months earlyforecast Mar 31, 2011

Also in Allan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27180 in the federal list. How to read these figures.