St. Peter's Wastewater Plant Efficiency Upgrade

St. Peter's, Nova Scotia

completeWastewaterCC Top Up
Federal contribution
$70,667
Federal share33%

of $212.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of St. Peter's
Construction start
Apr 14, 2011(actual)
Construction end
Sep 13, 2011(actual)

Against the original forecast

  • Construction start22 months lateforecast Jun 1, 2009
  • Construction end2 months lateforecast Jul 15, 2011