Implementation of Broadband in Cockburn Island

Walford, Ontario

completeBroadband And ConnectivityCC Top Up
Federal contribution
$56,703
Federal share43%

of $131.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedJan 29, 2010
20102011
Built

Approved 8 months after the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Cockburn Island
Construction start
Aug 12, 2010(actual)
Construction end
Oct 21, 2011(actual)