Arichat Sewage Pumping Stations Upgrade

Arichat, Nova Scotia

completeWastewaterCC Top Up
Federal contribution
$250,000
Federal share33%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
May 10, 2010(actual)
Construction end
Jan 30, 2011(actual)

Against the original forecast

  • Construction start11 months lateforecast Jun 1, 2009
  • Construction end10 months lateforecast Mar 31, 2010

Also in Arichat

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27405 in the federal list. How to read these figures.